A new paved road through an established residential district, linking the Fourth and Fifth Ring Roads to ease traffic and serve local residents.

A new road in the heart of a neighbourhood

We built this road for Benghazi Municipality inside a lived-in neighbourhood, which called for careful planning of plant and truck movements to keep residents safe and maintain access to their homes and shops throughout the works.

The works covered removal of the old layers, excavation and grading of the alignment, supply, spreading and compaction of the base courses, and finally laying and rolling the asphalt. The road was completed in three months, on the approved schedule.

How the road was built

  • Removal of old layers, excavation and grading
  • Supply, spreading and compaction of base courses
  • Laying and rolling the asphalt layers
  • Traffic management and site safety in a residential area

Road details

  • ClientBenghazi Municipality
  • LocationShabna (D), Benghazi
  • Duration3 months
  • PeriodAugust – November 2021
  • StatusHanded over November 2021